Sunday, February 14, 2016

Sloppy pool construction practices

Which of these sloppy construction practices is your pool builder guilty of using? 

No soils reports (even in differential soils)?
Undermining the foundation of a house by digging too close?


Using flexible PVC tubing (meant for portable above grade spas) because they were too lazy to heat bend pipe?


Only install 2-bar bond beams?
Install reinforcing steel or pins in contact with the forms or earth?


Place your pipes directly on the earth, because trenching to place them below grade is too difficult?


Use the same steel schedule for every single project or utilize generic / mail order engineering without regard to surcharges (soil conditions, building foundations, hydrostatic conditions, wind loads, etc) ?
Use flimsy forms that do not provide a solid surface to shoot against (as required by ACI & ASA) ?



If your pool builder does not know why these practices are forbidden or against industry practices, then they need some training and education. Unfortunately, this is an industry of "on the job training"... but if the people they learned from were doing it wrong... the tradition continues !

Did you know that the International Building Code (IBC) and International Residential Codes (IRC) REQUIRE soils reports, project specific structural engineering (structures must be designed to overcome the anticipated loads) and minimum shell thicknesses? Some states have adopted their own more restrictive building codes (but they are based upon the IBC & IRC - e.g. CA & FL).

Most building departments that do not enforce their adopted building codes, do so, out of ignorance. The liability in the event of a failure, falls on the contractor, as the government has immunity. It is your builders responsibility to know the codes and to follow them.

Just because they have done it that way for 35 years, does not make it RIGHT... SAFE or LEGAL.

You should be constantly learning, something new everyday - then putting that into practice.  If you think that you "know it all," then it is time to retire.

I cannot count the number of times that pool builders in various courses or lectures have come up to me after and said, "You know we've been doing it that way for XX years. I never knew that it was wrong," "That explains why we have that type of failure constantly occurring," "I wish someone would have taught me the correct way years ago. It would have saved me thousands of dollars in remedial repairs."

EDUCATION is cheaper that demolition and lost consumer confidence.

No, I'm not saying all of this because I've been sued or have a vested financial interest in any education programs. I am saying this because I want to elevate the practice of building pools and make this industry better. Anyone who knows me, knows that though there are various techniques, there is only one way of doing something - the RIGHT WAY ! 

How do you know that your pool is being built in compliance with the building codes, if the local building inspector does not know what he is looking at?  Hire an independent inspector or "owner's representative" to ensure that your project is built "per code."

Paolo Benedetti, SWD Aquatic Artist, Watershape Consultant, Expert Witness, International Construction Management 
Contact the author at: info@aquatictechnology.com or 408-776-8220 
"Creating water as art."™ 
Aquatic Technology Pool and Spa© 
©www.aquatictechnology.com 
All rights reserved.

Monday, August 12, 2013

Soils Reports and Project Structural Engineering are the law

Swimming pool expert witness explains why soils reports and project specific structural engineering are required by law (the building codes).

Structural Engineering 


Swimming pools must be designed to withstand any force that will be exerted upon the structure.  These forces are called "surcharges."  The leading surcharge on an in-ground pool are the soils surrounding the pool itself.

Soils

The soils must be able to support the structure and prevent movement.  Soil conditions can very from lot to lot in the same subdivision.

For example, these soils can be expansive, non-supportive, prone to sliding or vertical uplift or subject to liquifaction.

One cannot ascertain the characteristics of the underlying soils by looking at the top soil.  That is unless they are Superman with x-ray vision.

Structural Engineer needs a soils report

A structural engineer cannot design the structure, without knowing the characteristics of the underlying soils.

Therefore, they need a soils report to tell them what site conditions are present.

Required by Law (Building Codes)

The 2012 International Swimming Pool and Spa Code states:
802.1 Materials of components and accessories.
The materials of components and accessories used for permanent inground residential swimming pools shall be suitable for the environment in which they are installed. The materials shall be capable of fulfilling the design, installation and the intended use requirements in the International Residential Code.
802.2 Structural design.

The structural design and materials shall be in accordance with the International Residential Code.  


The International Residential Code goes into further depth as to the requirement for project specific engineering, soils reports, minimum concrete strengths, foundation requirements, shotcrete strengths, rebar installation, special inspectors, laboratory testing, etc.

Since the 2012 International Swimming Pool and Spa Code has been incorporated into the International Building Code, which is THE building code for the entire United States... it has defacto become the swimming pool code for the United States.  

The Swimming Pool Code's counter reference to the IBC and IRC places a lot of additional minimum specifications and requirements on the construction of a concrete swimming pool or spa (gunite/shotcrete).

It helps to know the law.


Paolo Benedetti 
Aquatic Artist, Watershape Consultant, Expert Witness 
"Creating water as art."™ 
Aquatic Technology Pool and Spa ©www.aquatictechnology.com

Friday, March 15, 2013

Swimming Pool - Minimum Concrete Strengths & Special Inspections

4,000 PSI Shotcrete - there ought to be a law...
aah, but there is and it is rarely adhered to or understood.

Code Requirements 

Variations of the International Building Code (IBC) have been adopted in every state of the US, except Minnesota.  The IBC has many sub-books, the most popular being the International: Residential Code (IRC), Mechanical Code, Plumbing Code, Electrical Code, and yes, Swimming Pool Code (ISPC).

No one code addresses everything one needs to comply with in order to build anything, whether it is a wood framed house, steel barn, concrete bridge or swimming pool.  Instead, one needs to comply with the various portions that apply to their project that are found in the different areas of various codes.

Concrete & Shotcrete Codes

The IRC contains sub-chapters on concrete construction and shotcrete.  Shotcrete (wet or dry mix methods of pneumatically applying concrete) is concrete construction.  The code recognizes this, so the shotcrete chapter specifies that the chapter on concrete shall also apply to shotcrete.

The concrete chapter specifies that the MINIMUM strength for the construction of any concrete structure is 3,000 PSI.  But, the chapter also directly references and incorporates ACI 318-96 (1996), which specifies that shotcrete shall be 4,000 PSI.

Further complicating matters, the chapter on shotcrete makes direct reference to and incorporates ACI 506R-90 (1990), which also specifies that shotcrete shall be 4,000 PSI.

So, merely by reference and inclusion in the IRC/IBC, the American Concrete Institute (ACI) has set the minimum building code standard for shotcrete construction at 4,000 PSI. 

Special Inspections & Testing

The IRC sub-chapter on shotcrete also requires special inspections of the following (not a totally inclusive list):
reinforcing steel
shotcrete process and placement
initial curing process
mix design
testing and sampling
28 day compression testing (laboratory)  

A special inspection, is not the regular city building official's inspection.  Rather it is a qualified inspector from an independent observation and testing firm.  The special inspector (sometimes called a deputy inspector) is required to stand and observe the entire shotcrete placement process.

They are also required to monitor the mix designs and obtain test panels for later compression testing.  This does not mean that the shotcrete company shoots material into a test cylinder.  Instead, they must build panels of a prescribed size and actually shoot the material just as if they were creating the structure.

Structural Engineers  

In an effort to "save" contractors the expense of special inspections and worse yet, the oversight of an independent inspector, some structural engineering firms specify only 2,500 PSI shotcrete.

The code requires that concrete specified over 2,500 PSI be subject to all of the above special inspections.  But, because the code specifically states that shotcrete shall be a minimum of 3,000 PSI, this maneuver is no longer valid.  Special inspections and testing can no longer be danced around - they are the law.  While not every state has included the specific shotcrete chapter in their adopted versions of the IRC, it becomes included through the inclusion of the ACI standards.

So, now if your structural engineer specifies only 3,000 PSI, they can still be in violation of the building code.  Because, through the reference of the ACI standards, the IBC/IRC (and the even more restrictive California Building Codes) now make 4,000 PSI shotcrete and special inspections THE STANDARD.


Paolo Benedetti 
Aquatic Artist, Construction Consultant & Expert Witness 